• CATEGORIES
    • All Categories
    • Antiques
    • Art
    • Automotive
    • Baby
    • Beauty & Fragrances
    • Books & Magazines
    • Business & Industrial
    • Cameras & Photo
    • Cell Phones, PDAs & Accessories
    • Clothing & Shoes
    • Collectibles
    • Computers & Networking
    • Crafts
    • Electronics
    • Entertainment Memorabilia
    • Flowers & Gifts
    • Glass & Pottery
    • Health & Personal Care
    • Home & Garden
    • Jewelry & Watches
    • Misc
    • Movies & DVDs
    • Music
    • Office Supplies
    • Real Estate
    • Services
    • Sex Stuff
    • Sports & Outdoors
    • Sports Memorabilia
    • Tools & Hardware
    • Toys, Games & Hobbies
    • Video Games
  • COMMUNITY
  • FAQ
  • SELL
  • AU
    • US
    • UK
    • AU
  • Cart
eCrater
  • Sign Up
  • Login
  • Home >
  • All Categories >
  • Books & Magazines >
  • eBooks(10730)
$13.99 Add to Cart

PM571 Week 3 Project Time and COst Exercises

PM571 Week 3 Project Time and COst Exercises

More than 10 available, 1 sold

Details

Shipping: Australia: free (more destinations)

Condition: Used

Tweet    
  • Description
Assignment Content
Complete Exercises 1, 2 and 3, starting on p. 150, in Chapter 5 of Project Management.
Format your paper consistent with APA guidelines.
Submit your answers in a Microsoft® Word document, including all calculations and the final answer.

Chapter 5
Exercise 1
Calculate the direct cost of labor for a project team member using the following data:
Hourly rate: $40/hr
Hours needed: 80
Overhead rate: 40%

Exercise 2
Mrs. Tolstoy and her husband, Serge, are planning their dream house. The lot for the house sits high on a hill with a beautiful view of the Appalachian Mountains. The plans for the house show the size of the house to be 2,900 square feet. The average price for a lot and house similar to this one has been $120 per square foot. Fortunately, Serge is a retired plumber and feels he can save money by installing the plumbing himself. Mrs. Tolstoy feels she can take care of the interior decorating.

The following average cost information is available from a local bank that makes loans to local contractors and disperses progress payments to contractors when specific tasks are verified as complete.

24 % Excavation and framing complete
8 % Roof and fireplace complete
3 % Wiring roughed in
6 % Plumbing roughed in
5 % Siding on
17 % Windows, insulation, walks, plaster, and garage complete
9 % Furnace installed
4 % Plumbing fixtures installed
10 % Exterior paint, light fixtures installed, finish hardware installed
6 % Carpet and trim installed
4 % Interior decorating
4 % Floors laid and finished

a. What is the estimated cost for the Tolstoy's house if they use contractors to complete all of the house?
b. Estimate what the cost of the house would be if the Tolstoys use their talents to do some of the work themselves.

Exercise 3
Below is a project WBS with cost apportioned by percents. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables?
Design?
Programming?
In-house testing?
What weaknesses are inherent in this estimating approach?

ANSWER WILL
... [Full Description]

Title of Image

Seller Information

Seller

homework 5/5 Stars
  • Contact Seller
  • 96.53%, 4120 sales
‹ ›
View Store

Location

  • US, CA

Payment

  • Credit Cards
  • Credit Cards accepted via:
  • PayPal

Additional Info

  • About
  • Terms and Policy
  • Contact Info
  • FAQ
  • © 2026
  • ·
  • eCRATER
  • ·
  • Get your free online store
Last Updated: 6 Apr 2026 05:09:38 PDT
  • about
  • ·
  • terms
  • ·
  • privacy
  • ·
  • dmca
  • ·
  • contact
  • ·
  • news
Follow Us